One of the main challenges facing deep quarries today is ensuring the stability of the quarry board. The article considers the influence of natural and man-made factors of mining operations on the stability state of the quarry sides.To maintain the quarry side stability, the efficiency of mining operations and security work, the results have been presented using the program. When determining the results, the "VNIMI" method is used, which uses the algebraic sum of forces, as well as the "master" program with the addition of additional factors. The research was carried out on 4 characteristic profiles in the sides of the quarry using the VNIMI methodology and the multifunctional computer program "Ustoi", as well as the procedure for calculating the stability margin coefficient. The calculation results  calculations show that with increasing the General angle of the side, the margin coefficient decreases, but the width of the collapse prism increases.Summing up, we can say that when calculating the stagnation of the Board, using the "master" program, the change in the stagnation reserve coefficient is given and it is recommended to adhere to it for quarry boards with a height of 500 meters and higher.

  • Ссылка в интернете
  • DOI
  • Дата создание в систему UzSCI 13-04-2021
  • Количество прочтений 245
  • Дата публикации 20-11-2020
  • Язык статьиIngliz
  • Страницы99-104
English

One of the main challenges facing deep quarries today is ensuring the stability of the quarry board. The article considers the influence of natural and man-made factors of mining operations on the stability state of the quarry sides.To maintain the quarry side stability, the efficiency of mining operations and security work, the results have been presented using the program. When determining the results, the "VNIMI" method is used, which uses the algebraic sum of forces, as well as the "master" program with the addition of additional factors. The research was carried out on 4 characteristic profiles in the sides of the quarry using the VNIMI methodology and the multifunctional computer program "Ustoi", as well as the procedure for calculating the stability margin coefficient. The calculation results  calculations show that with increasing the General angle of the side, the margin coefficient decreases, but the width of the collapse prism increases.Summing up, we can say that when calculating the stagnation of the Board, using the "master" program, the change in the stagnation reserve coefficient is given and it is recommended to adhere to it for quarry boards with a height of 500 meters and higher.

Имя автора Должность Наименование организации
1 Mahmudov D.R. dotsent TDTU
2 Kadirov V.R. Assistant TDTU
3 Aripova K.A. o'qituvchi TDTU
Название ссылки
1 1. Rakhimov V. R., Murzaykin I. Ya. determination of the neotectonic movements of rock blocks geodetic methods/J. Mountain Bulletin of Uzbekistan, no. 2, 2008. P. 13-21.
2 2. Finiston Open Pit mine (Super Pit gold mine). https://www.mindat.org/loc-192453.html/
3 3. Finiston Open Pit “Super Pit” Gold Mine. https://www.mining- technology.com/projects/superpitgoldmineaust/
4 Umarov F. Ya., Nasirov U. F., Petrosov Yu. E., Kadirov V. R. Managing the state of responsible engineering structures in deep quarries // Bulletin Tashkent state technical university. -2016. - №1. - P. 205-209.
5 F. Ya. Umarov. Monitoring the condition of the slopes of the sides of a deep quarry Mountain information and analytical Bulletin. - Moscow state University (Moscow), 2013, № 5. P. 88.
6 Markov A.V. On the calculation of tectonic stresses in the earth's crust of South-Western Uzbekistan // Bulletin Tashkent state technical university. -2008. - №4. - P. 160-166.
7 P. A. Shemetov, F. Ya. Umarov. Seismic safety technology of BWR in the near-contour area of the quarry and near critical structures Mining information and analytical Bulletin. - Moscow state University (Moscow), 2013, № 8. P. 221.
8 Methodological guidelines for observations of deformations of boards, sections and dumps, interpretation of their results and stability forecast. L., VNIMI, 1987. P. 45.
9 Popov V. N., Shpakov P. S., Yunakov Yu. L. Managing the stability of quarry slopes. Moscow. Gornaya kniga publishing house, 2008. P. 112.
10 10. Results of MAX decoding, preliminary assessment of geodynamic and seismic activity of the "M" quarry territory. PGO Aerology report, VNIPI funds PT. Arch. №. A-893-91, 2018.
11 11. Seismic zoning of the territory of the USSR. Methodological foundations and regional map description, 1978, Bune V. E., Gorshkov G. P. M., Nauka, 2016. P. 24.
12 12. D. R. Makhmudov, Yu. E. Petrosov. Production technology of drilling and blasting operations in deep open pit mines of Uzbekistan. Mining information and analytical Bulletin. - Moscow state University (Moscow), 2017, № 5. P. 331.
13 13. J. Wesseloo and J.Read, Acceptance Criteria, in Open Pit Slope Design, CSIRO, Lieden, 2013, P. 221.
14 B. R. Rakishev, A. N. Shashenko, A. S. Kovrov. Geomechanical assessment of the stability of the sides of quarries and dumps. Almaty: "Gylym" NAS RK, 2017. - 234 p. ISBN 978-601-323-103-7.
15 Report on research work. Assessment of the geomechanical state of the pribortovogo array of the "M" quarry with consideration of influencing factors on the basis of geodynamic zoning / / Tashkent state technical university. 2008. - P. 160-166.
16 Soren K., Budi G., Sen P. Stability analysis of open pit slope by finite difference method //International journal of Research in Engineering and Technology. 2014. Vol. 3. Iss. 5. P. 326.
17 Makhmudov D.R., Kodirov V.R., Karimov Sh.V., Hamraev Y.R. Research of the influence of technological factors on the state of the sides of deep quarries // Вестник ТГТУ. – Ташкент, 2020. – №3. – P. 122-129.